Development of Our New Institute

Our Current Institute

Our New Institute

Phase 2: School Building East Wing

27200000
218712

Phase 2 – Stage 1: Substructure & Ground Floor

3400000
218712

Total Funds Invested in Project

152000000
11547380

* Last updated 1 October 2024

Work Completed

AlḥamduliLlāh, our building plan has been approved by council, which concluded Phase 1 (the pre-construction phase) of the project. As part of Phase 1, the land was acquired, rezoned, and the development contribution and scrutiny fees paid. Majority of the initial and underground civil work was also completed, which included site preparation, bulk earthworks, and the installation of water, stormwater, sewerage, and cabling networks. Majority of the front boundary wall has also been built and the rear fencing erected.

Work In Progress

We have now progressed to Phase 2, which comprises the construction of the East Wing of the School Building and will be able to accommodate our current student body. This will allow us to move to our new premises the soonest. However, our approved building plan is only valid for 12 months; thus, we have until latest mid-April 2025 to raise the funds and commence construction.

This is an ideal opportunity to establish a Ṣadaqah Jāriyah (continuous charity) on behalf of yourself or your loved ones (both alive and deceased). May Allah SWT accept all our efforts, Āmīn.

Local Donations






* International Visa and Mastercard Credit/Cheque cards accepted.

Direct EFT

The DUAI Foundation Trust
Building Fund

Bank: Absa

Branch Code: 632005

Account type: Savings

Account Number: 92 9273 0919

Reference: Donor’s Name/Business name

Proof of Payment: [email protected]

International Donations

Please consider setting up a monthly donation

Enquiries