
Development of Our New Institute
Local Donations
Recurring Donation

* Please note, the first donation will be made on the day that you set up your recurring donation while the remaining donations will be made on the debit order date that you specified.
Once-off Donation

![]()
![]()
* International Visa and Mastercard Credit/Cheque cards accepted.
Direct EFT

The DUAI Foundation Building Fund
Bank: Absa
Branch Code: 632005
Account type: Savings
Account Number: 92 9273 0919
SWIFT code: ABSAZAJJ
Reference: Nature-Donor’s Name/Business name
Nature: Lillāh or Ṣadaqah
Proof of Payment: [email protected]
International Donations

Please consider setting up a recurring monthly donation
Development of Our New Institute
Phase 2 – Stage 2: Structural Frame
Phase 2 – Stage 3: Roof & External Envelope
Phase 2: School Building East Wing
Total Funds Invested in Project
* As at 12 December 2025
Work Completed
AlḥamduliLlāh, our building plan has been approved by council, which concluded Phase 1 (the pre-construction phase) of the project. As part of Phase 1, the land was acquired, rezoned, and the development contribution and scrutiny fees paid. Majority of the initial and underground civil work was also completed, which included site preparation, bulk earthworks, and the installation of water, stormwater, sewerage, and cabling networks. Majority of the front boundary wall has also been built and the rear fencing erected. We have also developed the electrical plans.
We have now progressed to Phase 2, which comprises the construction of the East Wing of the School Building and will be able to accommodate our current student body. We have also broken ground on the Masjid (Phase 3).
AlḥamduliLlāh, we have completed the construction of the foundation and ground floor (Stage 1) for both Phase 2 and Phase 3. This involved: clearing the site; excavating and smoothing the foundation trenches; casting the foundations; building the foundation walls to ground floor level; filling the cavity walls and columns; backfilling the trenches; compacting the earth; installing the waterproofing underlay, insulation, steel reinforcement, and electrical and plumbing conduits for the ground floor slab; casting the ground floor slab. We have also purchased 120,000 face bricks and 28,000 clay bricks for the external envelope.
Work In Progress
Construction will pause for the builders’ holiday and resume in January 2026 with the construction of the structural frame (Stage 2) and the roof & external envelope (Stage 3).
This is an ideal opportunity to establish a Ṣadaqah Jāriyah (continuous charity) on behalf of yourself or your loved ones (both alive and deceased). May Allah SWT accept all our efforts, Āmīn.
